Week Commencing 07 July 2025

Roads

weBPAGE.jpg

Clarence Town Road Segment 5 South of Dungog Road - Works ongoing including pavement stabilisation works and batter treatments. Traffic lights will be in operation to manage the flow of traffic, some delays are to be expected during this time.

Dowling Street, Dungog -  Pavement works now completed, guardrail installation works scheduled to follow.

Fosterton Road, Dungog -  Project works ongoing to continue with pavement and drainage works.

Glen Martin Road - Works on this project continue to remain on hold due to flood recovery works.

Pinebrush Road - Works on this project continue to remain on hold due to flood recovery works.

Webbers Creek Road Footpath - Footpath works from the Paterson Public School to Prince Street scheduled to continue.

SEALED ROADS

Tar Patching - Martins Creek Road, Paterson Urban, Bingleburra Road, Glendonbrook Road, Paterson River Road.

Heavy Patching - Gresford Road, Bingleburra Road

Roadside Slashing - Gresford Road, Summer Hill Road, Fishers Hill Road

UNSEALED ROADS

Chichester Road, Chads Creek Road, Welshmans Creek Road, Gardiners Road, Salisbury Gap Road, Allyn River Road, Fosterton Road, Ebsworth Road, Gabulah Road River Crossing

For real-time information about roads and changed traffic conditions please refer to www.livetraffic.com

Bridges

30.06.2025 2.JPG

New Clarence Town Bridge - Earthworks and piling works are scheduled to continue. Traffic lights in operation to manage the flow of traffic, some delays are to be expected during this time.

For real-time information about roads and changed traffic conditions please refer to www.livetraffic.com

Parks & Sporting Grounds

Dungog Pool - Concourse replacement - removal of existing concourse continuing.

PARK MAINTENANCE

 Dungog, Vacy, Martins Creek and Paterson areas

Buildings

Clarence Town Community Centre - Ceiling & cornice repair works required following May natural disaster event, maintenance works complete.

Williams River Holiday Park - Electrical and plumbing repairs in progress and cleaning completed 3 July following the May natural disaster event on lower amenities building