Abelard Street and Mackay Street Roundabout Construction – Works are continuing, with kerb and drainage works. The intersection will be closed for the duration of the project, with detours in place until completion. Resident and property access to both Abelard Street and Mackay Street will be maintained throughout the works. The works are expected to be completed by the end of June 2026.
Fishers Hill Road, Fishers Hill - Works are continuing on pavement, with crews now progressing to headwall installation and ongoing culvert works.
MAINTENANCE ACTIVITIES
Sealed Roads
Tar Patching - Clarence Town Road, Dungog Road, Brentwood Road, Stroud Hill
Roadside Slashing - Clarence Town Road & Clarence Town Urban
Unsealed Roads
Maintenance Grading - Quart Pot Creek Road